Midwest Transportation Consortium

Guidelines for a Roadway Management System (RMS) for Local Governments

Principal Investigator
Anil Misra
Professor of Civil Engineering, University of Missouri - Kansas City

Co-Principal Investigator
Ali Roohanirad
Design Chief, Jackson County, Missouri

Research Assistant
Prapon Somboonyanon
Graduate Assistant, University of Missouri - Kansas City

Preparation of this report was financed in part through funds provided by the U.S. Department of Transportation through the Midwest Transportation Consortium.
MTC Project A-01 (Year One, 2000)

Midwest Transportation Consortium
c/o Iowa State University
2901 South Loop Drive, Suite 3100
Ames, IA 50010-8634
Telephone: 515-294-8103
Fax: 515-294-0467
www.ctre.iastate.edu/mtc/

Final Report | October 2003

TABLE OF CONTENTS

EXECUTIVE SUMMARY

1. INTRODUCTION

2. SURVEY RESULTS

2.1. Survey of Local Agencies

2.2. Literature Survey

3. BACKGROUND INFORMATION

3.1. Definitions

3.2. Pavement Types

3.3. Low-Volume Flexible and Built-Up Road Pavements

3.4. Pavement Distresses

4. INVENTORY METHODOLOGY

4.1. Type of Segments

4.2. Referencing Methods

4.3. Defining the Facility Network into Segments

4.4. Network Level versus Project Level

5. EVALUATION OF CURRENT CONDITION

5.1. Pavement Condition Rating by Visual Inspection

5.2. Pavement Condition Index

6. INTEGRATION OF RMS WITH GEOGRAPHICAL INFORMATION SYSTEMS

6.1. Systems Displaying RMS Information on Maps

6.2. Components of GIS

6.3. Approach to Establishing a Central Database

7. GENERATING STRATEGIES AND ALTERNATIVES FOR MAINTENANCE, REHABILITATION, AND RECONSTRUCTION (MR&R) ACTIONS

8. PAVEMENT PERFORMANCE PREDICTION MODEL

9. LIFE CYCLE COST ANALYSIS

9.1. Total Cost of Each Strategy

10. PRIORITY PROGRAMMING

10.1. Mathematical Formulation of Priority Index

11. REPORT GENERATING METHODS

12. SUMMARY

13. REFERENCES

Appendix A: Questionnaire and Detailed Summary of Local Government Survey (510 kb pdf)

Appendix B: Forms for Data Collection (510 kb pdf)

Appendix C: Distress Types for Low-Volume Flexible and Built-Up Roads (2 mb pdf)

Appendix D: Deduct Value Curves for Low-Volume Flexible and Built-Up Roads (4.7 mb pdf)

Appendix E: Corrected Deduct Value Curves for Low-Volume Flexible and Built-Up Roads (697 kb pdf)

Appendix F: Repair Strategies Flow Charts (697 kb pdf)

Appendix G: Deterioration Curves of Actual Data and Predicted Curves (95 kb pdf)

LIST OF FIGURES

Figure 1. Condition Evaluation Flow Chart

Figure 2. Qualitative Expression in Terms of Pavement Quality Associated with PCI

Figure 3. Flowchart Presenting the Procedure to Calculate PCI

Figure 4. Maintenance Activity and Time for Each Level of Service Based on PCI

Figure 5. Typical Maintenance and Rehabilitation Feasible Actions for Flexible Pavement

Figure 6. Typical Maintenance and Rehabilitation Feasible Actions for Chip Seal Roads

Figure 7. Typical Maintenance and Rehabilitation Feasible Actions for Cold Mix Roads

Figure 8. Typical Maintenance and Rehabilitation Feasible Actions for Aggregate Surface Roads

LIST OF TABLES

Table 1. Examples of Flexible Pavement Distress Definitions

Table 2. Examples of Rigid Pavement Distress Definitions

Table 3. Examples of Aggregate Road Surface Distress Types

Table 4. K1 and K2 Values Using Equation 3 to Predict PCI for Selected Pavement Age

Table 5. Examples of the Comparison between Actual PCI and Predicted PCI

Table 6. Traffic Factor Based on ADT

Table 7. Roadway Functional Classification Factor 46 Table 8. Roadway Location Factor

Table 9. Maintenance History Factor

Table 10. Pavement Riding Quality Factor

EXECUTIVE SUMMARY

The objective of the proposed guidelines for a roadway management system (RMS) is to describe a framework for a modular and user-friendly RMS that will assist local government agencies of all sizes in coordinating and planning routine and preventive maintenance, rehabilitation, and reconstruction. These guidelines include a step-by-step procedure to establish a customized RMS for local government agencies. The resulting RMS, based upon the proposed guidelines, will be a systematic methodology that can assist local government agencies to evaluate current pavement conditions, identify problems on pavements, select the best repair and maintenance strategies with the minimum cost, and generate a schedule and priority program for these actions at both project and network levels at both the present time and the future.

As part of these guidelines, we also report the results of a nationwide survey of local government roadway management practices. A questionnaire was developed as part of this survey and sent out to local government agencies throughout the United States. This information was then used to establish the proposed RMS guidelines that are relevant for local government agencies’ needs and expectations. In addition, a literature survey was conducted to review current roadway management systems and research, and to reduce the duplication of research, information, or training materials that have been developed by other government agencies or private consultants. Furthermore, the information from both survey methods was evaluated, refined, and customized to the proposed RMS guidelines.

Detailed background information on various aspects of a roadway pavement and an RMS is also given in these guidelines to ensure consistency of usage and understanding since these terms and definitions may vary from one agency to another. The information includes definitions and terms related to pavements, types of pavement, types of pavement distress, etc.

Then, a section on inventory methodology is included. An inventory methodology is established for use in the data collection process. It is imperative that only necessary information be collected to reduce time and cost in the data collection process. This section also provides terms and definitions used in the inventory program, referencing and defining methods for the roadway network, and the understanding between project and network levels. This information is expected to clarify the scope and level of responsibility for local government agencies.

Once the data inventory is established, the data collection process can be initiated to gather information from concerned pavements within the roadway network. The data used to evaluate the current pavement condition can be obtained by a variety of methods such as visual inspection rating, nondestructive testing, destructive testing, and others. Moreover, there are several mathematical indices that indicate the current pavement condition and that are widely used by local government agencies, such as the Present Serviceability Index (PSI), International Roughness Index (IRI), and Pavement Condition Index (PCI). These guidelines also provide the step-by-step procedure to obtain the PCI value for different low-volume flexible and built-up pavement types as well as different maintenance strategies. In the proposed guidelines, the PCI value forms the basis for establishing the other components as well as developing the coordination among the components of an RMS.

The integration of an RMS with a geographical information system (GIS) is another approach to achieve the long-term use of an RMS by updating the data on pavements within the roadway network. This report presents the advantages acquired from the integration of an RMS with GIS as a platform, details of systems displaying RMS information on maps, components of GIS, and the approach to establish a central database.

Furthermore, these guidelines present a method to generate the maintenance, rehabilitation, and reconstruction actions in order to maintain and improve the pavement performance based upon the PCI obtained earlier. This will help local government agencies to decide what repair and maintenance actions would be best suitable for concerned pavements.

Without a pavement performance prediction model, the future tasks and schedules cannot be effectively planned. A pavement performance prediction model is developed based upon the collected data on pavements to forecast the PCI value in the future. Therefore, by using this prediction model local government agencies will be able to predict future facility condition, analyze facility life cycle cost, and estimate the type and timing of maintenance and rehabilitation need regarding only the projected PCI.

There are a number of factors used to consider maintenance alternatives needed for pavements such as cost, duration of action, available resource, etc. Generally, the cost of each alternative is the primary factor that most local government agencies are concerned with due to the limited funding each year. In order to compare the cost of each strategy, life cycle cost analysis can be preformed. Consequently, a methodology for life cycle cost analysis is also provided in these guidelines.

Usually, local government agencies do not have enough funds to improve all segments within a roadway network although they have adequate information to identify problems on these segments. The priority program, therefore, is the solution for local government agencies to generate their budget and to numerically plan which concerned segment should be first taken care of. These guidelines identify the numerous factors affecting the priority index such as PCI, average daily traffic, roadway functional classification, roadway location, maintenance history, and pavement riding quality, and provide a methodology for obtaining the priority indices.

The final component of an RMS is to generate a report such that the elected board or council can approve the funds regarding local government agencies’ needs. It is imperative that the data and analysis be clear and easy to understand for those who are not technical experts or engineering professionals. These guidelines briefly demonstrate the tasks that should be considered and included in the proposed report. This will guide local government agencies to establish the proposed report for their own customized RMS.

1. INTRODUCTION

Managing, computing, and networking assets is one of the most problematic issues of modern networks. A roadway management system (RMS) is a systematic methodology for identifying, prioritizing, and cost-effectively addressing maintenance needs of government agencies, based on techniques and resources that are matched to local circumstances.

This report contains detailed guidelines for implementing a total RMS and is intended for use by those who are responsible for managing and maintaining roadway pavement. These guidelines discuss the necessary procedures to determine the RMS needs of an agency and are also designed to assist local government agencies of all sizes, managers, engineers, and maintenance personnel, in making an informed and cost-effective decision about the pavement components for which they are responsible. The report also provides local government agencies with proven, practical tools, techniques, and procedures for developing a customized RMS, which will assist them to develop proactive maintenance plans.

An effective roadway management system should provide complete life cycle coverage, starting with the planning, and continuing until replacement or reconstruction. Through the automation of the maintenance processes, a roadway management tool can save time and provide accurate information on roads and other infrastructure by eliminating subjective judgment. The RMS can also help managers use good data to make objective judgments in selecting maintenance strategies.

Typically, a roadway management system includes a set of analysis tools that may be used by the asset manager for evaluating alternative strategies in a systematic and coordinated manner, with the objective of operating a network system at minimum cost and maximum efficiency. Such a system involves the following key elements:

An efficient RMS should integrate easily with other infrastructure models. This feature allows a local agency to plan, schedule, and determine the needs budget and make objective decisions on when, where, how, and what to do. Also, this allows the managers to use their resources as a complete system.

An RMS will help local government agencies in planning, programming, design, maintenance, rehabilitation, reconstruction, and monitoring facilities’ conditions. In other words, with an RMS, information will be available on a facility’s condition and performance, which can help managers to develop a plan schedule and prepare short- and long-range requirements. The total goal of an RMS is to achieve maximum total return on the public’s capital.

2. SURVEY RESULTS

2.1. Survey of Local Agencies

A questionnaire was developed to survey local governments regarding the current roadway management practices of the local government in the areas of pavement management, bridge management, and signal management. The main purpose of the survey was to gather information about the tools used and developed by local government agencies throughout the United States to manage their roadway networks. Specifically, the survey’s intent was to explore the basis and the methodologies of such tools as well as the expectations from the use of these tools. The questionnaire, given in Appendix A, was mailed to 300 local governments, and 34 responses were received. The survey result shows that an RMS has been used as early as in the 1970s; however, many government agencies applied an RMS to their program only in the early 1990s. The survey results were analyzed to develop an inventory of current techniques, ideas, technology, and research materials related to roadway management systems that are appropriate to most local government agencies. A detailed summary of the survey results can be found in Appendix A.

The survey results show that more than 90 percent of roads in survey areas are flexible and built-up roads, including chip seal, cold mix, and gravel roads. Consequently, these pavement types should be seriously considered in the development of a new RMS, such that the developed systems can be efficiently used on these pavement types. Moreover, there is a clear need for methodologies to determine the pavement condition for such pavement types.

The method used to determine the pavement condition is a particularly important procedure for an RMS. There are various techniques used by local government agencies to verify the pavement condition such as the International Roughness Index (IRI), PAVER, riding quality, Present Serviceability Index (PSI), etc. Another technique called the Pavement Condition Index (PCI) has been developed relatively recently and is currently in use by several local government agencies throughout the United States. Almost 40 percent of our survey respondents utilize the PCI technique for pavement evaluation. PCI is the numerical indicator to determine pavement condition based on a variety of factors, and the current PCI can be determined according to the observed condition data of a pavement.

In addition to the techniques to evaluate current pavement condition, the pavement performance prediction model is also an important element of an RMS. However, these prediction models have not been widely established, especially for the pavement types, mentioned above, that are of most interest to local government agencies. Less than 25 percent of our survey respondents have used prediction models that are typically based upon their experience and the historical data they have collected. It is reasonable to emphasize that without an efficient prediction model an RMS cannot be well planned.

The processes used to make decisions on asset management actions such as maintenance, rehabilitation, or reconstruction (MR&R) is another important procedure of an RMS. More than 60 percent of the agencies surveyed have chosen life cycle cost analysis for economic evaluation and used the results to establish their strategy, schedule, and funding needs programs. The other agencies report that they use historical data and experience, along with available resources, to make decisions of asset management actions.

From the survey results, the agency expectations from the use of an RMS were also collected and analyzed. Almost 50 percent of the respondents suggested five different sets of items that local government agencies expect from a proposed RMS. These include (1) a pavement data collection method, (2) pavement life cycle cost analysis, (3) a pavement condition evaluation method, (4) a pavement performance model, and (5) an integrated management system that includes various assets. In addition, respondents also suggested the integration of geographical information systems (GIS) and global positioning satellite systems with the RMS. They also expressed a need for a user-friendly, flexible, and affordable RMS.

Considering the wide range of expectations from roadway management systems, we conclude that an RMS is best designed keeping an individual local government agency’s need as a primary goal. However, for portability, consistency, and to some extent uniformity between RMSs, certain underlying guidelines need to be applied during an RMS’s development. Consequently, this report focuses on developing guidelines and standards that may be used by a local government agency to develop its RMS.

2.2. Literature Survey

In addition to the survey of local government agencies, a review of the current state-of-art of roadway management systems was performed by searching materials related to RMSs such as articles, technical documents developed by government agencies, and textbooks. Following is a discussion of the findings from our literature search with special attention to the current issues related to roadway management systems.

The procedure developed by World Bank HDM Manager, Peru, is an attempt to approach road network management. The brief data collection process and survey results are provided. Based on the survey results, the analysis of data is conducted, and the recommended strategies for both paved and unpaved roads are presented. International Roughness Index (IRI) and Net Present Value (NPV) are important indicators used in the process to determine and prioritize maintenance activities (Liautaud 1996).

Al-Swailmi (1994) introduces the framework for municipal maintenance management systems. It is focused for use in cities rather than for rural road networks due to more factors affecting deterioration rate of the road network in cities than rural areas. Al-Swailmi provides the methodology used to develop a new system for a maintenance management system (MMS). Then, it is combined with city’s subsystem to eliminate conflicts between road and utility construction and maintenance activities and to provide the general concept of MMS with a cost-effective approach.

Livneh (1997) has described an approach for the development of deterioration curves of overlaid pavements. Livneh finds that the prediction model for pavement deterioration must be derived systematically because this model is very essential for the highway system. The material provides original deterioration curves and other formulations to predict the deterioration curves for overlaid pavements. A computation example is also demonstrated to support the equations developed in this paper.

Medina et al. (1999) have described a case study of using geographic information systems (GIS) with a pavement management system (PMS), specifically for low-volume roads. The paper presents the background of GIS and how it can be used to coordinate with PMS in order to help government agencies to efficiently generate strategies and eventually make decisions to improve pavements in the roadway network. The material also provides step-by-step guidelines for integrating these two systems, and then the method is used to estimate the cost of maintenance actions generated each year.

Hall et al. (2001) have described methodologies for generating rehabilitation strategies of highway pavements as part of the National Cooperative Highway Research Program (NCHRP), Project C1-38. Their report provides a set of procedures to help agencies in evaluating and selecting rehabilitation activities for highway pavements. The guidelines for life cost analysis of pavements are also given such that agencies can make decisions based upon their budgets.

3. BACKGROUND INFORMATION

Before any action may be initiated for establishing an RMS, it is important for a local government agency to acknowledge general information involving the pavement inventory such as definitions and terms used in pavements, type of pavement, type of pavement distress, etc. Since the terms, their definitions, and their usages may vary from region to region and from one local government agency to another, it is imperative to develop a common glossary in order to encourage consistency of usage and understanding. Therefore, in this section, we present a collection of terms and definitions that are widely used for describing pavement types and behavior.

3.1. Definitions

According to Asphalt Institute (1983), some terms defining pavement characteristics are described as follows:

In terms of maintenance and rehabilitation actions, several strategies are defined below:

3.2. Pavement Types

The types of pavements can be generally divided into three major groups: flexible or asphalt pavements, rigid or concrete pavements, and composite pavements (Huang 1993).

3.2.1. Flexible Pavements

There are three types of flexible pavements: (1) conventional flexible pavements, (2) full-depth asphalt pavements, and (3) contained rock asphalt mats (CRAM). Survey results described in Section 2 show that the flexible pavements make up approximately 55 percent of the total miles constructed within the surveyed areas.

Conventional flexible pavements. Conventional flexible pavements are composed of three main layers: bituminous surfacing, base, and subbase. The surfacing layer is divided into the wearing course and the binder course. The base course and subbase course can be constructed in the composite form by using different materials. The quality of materials used to construct layers and the intensity of stress vary from high for the top layer to low for the bottom layer. In addition to the main layers, a seal coat is applied on the top of pavement to provide skid resistance or to waterproof the surface. Also, a tack coat is placed between the surface and binder course, and a prime coat is applied between the binder and base course. The purpose of the tack coat and the prime coat is to provide bond between layers.

Full-depth asphalt pavements. The main concept for this type of pavement is to use as few different types of materials as possible. Usually only one material is used and is directly placed as one or more layers on the subbase course. These pavement types are easy to construct and cost-effective where other materials are not available in the local areas. If such a pavement is built in several layers then the tack coat must be applied between layers to provide an interlayer bond.

Contained rock asphalt mats (CRAM). There are four layers in CRAM pavement: starting from the top dense-graded hot mix asphalt, dense-graded aggregate, open-graded aggregate, and modified dense-graded hot mix asphalt. This type of pavement system is designed to reduce the compressive strain on the top of the subbase, prevent the contamination of aggregates by the infiltration of the subbase soils, improve fatigue resistance of the bottom asphalt layer, and reduce crack propagation in the surface layer. However, this type of pavement has not been widely used due to lack of design and construction standards.

3.2.2. Rigid Pavements

Rigid pavements are classified into four groups on the basis of pavement reinforcement and the load-transfer mechanism. Rigid pavements are mainly constructed from portland cement concrete with reinforcement bars. Survey results described in Section 2 show that rigid pavements make up approximately 6 percent of the total miles constructed within the surveyed areas. The four groups of rigid pavements are described below.

Jointed Plain Concrete Pavements (JPCP). These pavement types are built from plain concrete. The spacing of transverse joints varies from 15 to 30 feet depending on the type of aggregate, environment, and prior experience. Dowel bars may or may not be used in this type of pavement, varying by states.

Jointed Reinforced Concrete Pavements (JRCP). Steel reinforcement in any form provided in the pavement does not increase the structural capacity of the pavement but spacing between transverse joints. Although the amount of distributed steel increases with the longer joint spacing, the number of joints and dowel bars decreases, which practically reduces the maintenance costs of the pavement.

Continuous reinforced concrete pavements (CRCP). This type of pavement is used to eliminate transverse joints. It contains adequate steel reinforcement to carry the load in the cracked concrete sections.

Prestressed concrete pavements. Because of the weakness in tension in concrete, the pavement is prestressed in order to increase tension capacity of the concrete and to be able to carry more loads. Also, the thickness of pavements can be reduced, and the spacing can be largely increased. Prestressed concrete pavements are widely used in airport pavements not highway pavements due to high labor costs.

3.2.3. Composite Pavements

Composite pavements are a combination of a flexible hot mix asphalt layer and a rigid portland cement concrete layer, to provide a strong base and a smooth, nonreflective surface. This type of pavement is rarely built as a new construction although it is a desirable type of pavement from an economic viewpoint. These pavement types are usually found as a result of rehabilitating rigid pavements by using the flexible pavements as overlays.

3.3. Low-Volume Flexible and Built-Up Road Pavements

In general, all of the types of pavements described above are typically constructed in areas ranging from moderate to large communities. In small cities and counties, most pavements are built in the forms of (1) low-volume flexible roads and (2) built-up roads. Survey results described in Section 2 show that the low-volume flexible and built-up roads make up approximately 39 percent of the total miles constructed within the surveyed areas. Because of the wide use throughout the country of flexible and built-up roads in local government jurisdictions, this report will emphasize these pavement types.

The structure of low-volume road and built-up road pavements are usually the same as flexible pavements mentioned earlier. They are composed of a surfacing layer, a base course, and a subbase. The only difference in these two systems is the material used for the wearing surfaces. For the low-volume flexible pavements, the surfaces are often built from hot mix asphalt. The surfaces of built-up road pavements can be constructed of cold-mix asphalt, chip seal, or aggregate such as gravel. The properties of the low-volume flexible pavement structures are similar to the built-up pavement structures. Some significant properties of these two types are presented below:

3.4. Pavement Distresses

Distress is one of the most important factors that influence the performance of pavements. A variety of pavement distress can occur due to different causes such as load application, materials, environmental problems, etc. Huang (1993) recommends that each type of distress be treated separately by developing a different application depending on the cause of distress. Examples of pavement distresses are shown in Table 1 for flexible pavements, Table 2 for rigid pavements, and Table 3 for aggregate-earth surfaced roads (tables according to Modern Pavement Management, Hass 1994). The severity level of pavement distress is another important key in evaluating pavement condition. The severity levels in various types of distress in different types of pavement will be discussed in Section 5.2, “Pavement Condition Index.”

Table 1. Examples of Flexible Pavement Distress Definitions
(According to Hass 94)

Types of Distresses Description Severity Levels            Extent Measures
Alligator cracking Interconnected cracks caused by fatigue due to repeated loads L: Fine parallel longitudinal cracks
M: Network of cracks with some spalls
H: Well- defined pieces that may rock   under traffic and spalled at the edges
Square feet of surface area
Block cracking Interconnected cracks caused by shrinkage of the asphalt and daily temperature cycling. Size of block ranges from 1 to 10 feet. Generally occurs over a wide area of the pavement surface. L: Any filled crack or nonfilled cracks less than 3/8 inches.
M: Nonfilled cracks 3/8 to 3 inches. wide   or nonfilled cracks up to 3 inches wide surrounded by light random cracking
H: Any crack surrounded by random cracking or nonfilled crack more than 3 inches.
Square feet of surface area
Distortions Corrugations, bumps, sags, and shoving. Abrupt upward or downward displacements of the pavement surface. Distortions are evaluated relative to the effect on ride quality.  L: Cause vibration in the vehicle but do not require the vehicle to be slowed
M: Significant vibration in the vehicle, some reduction in speed is necessary for safety and comfort
H: Excessive vehicle vibration requires considerable speed reduction for safety and comfort
Square feet of surface area
Longitudinal and transverse cracking Cracks that are either parallel or transverse to the pavement centerline. Longitudinal cracks are generally related to construction or defects and transverse cracks are related to temperature variations and hardening of the asphalt. L: Any filled crack or nonfilled cracks less than 3/8 inches.
M: Nonfilled cracks 3/8 to 3 inches wide or nonfilled cracks up to 3 inches wide surrounded by light random cracking
H: Any crack surrounded by random cracking or nonfilled crack more than 3 inches.
Square feet of surface area
Patching and utility cuts Repair of the pavement with new material. L: Patch in good condition and does not affect ride quality
M: Moderate deterioration, some effect on ride quality
H: Severe deterioration, with high severity effect on ride quality
Area of patching
Rutting Depression in the transverse profile of the pavement surface. L: Less than 1 inch depth
M: 1 to 2 inch depth
H:  More than 2 in depth
Square feet of surface area

Table 2. Examples of Rigid Pavement Distress Definitions
(According to Hass 94)

Types of Distresses Description Severity Levels            Extent Measures

Blow-up and buckling


Slab expansion with insufficient joint width causes upward movement of the pavement at the joint. Rated relative to the effect on ride quality. L: Little effect on ride quality
M: Medium severity ride quality H: High severity ride quality
Rate two slabs as distressed for a joint blow-up and as one slab for a crack blow-up
Corner break Crack intersects the joints at the distance less than or equal to one-half the slab length on both sides. Crack extends vertically through the depth of the slab. L: Low severity crack with area defined by the break having little or no other cracking
M: Medium severity cracking with some medium severity cracks in the area defined by the break and the joint
H: High severity cracking and the area between the break and the joint is severely cracked
Extent measured by the number of slabs that are affected
Durability or D cracking Caused by freeze thaw expansion of large aggregate resulting in a breakdown of the concrete. L: Cracks are tight and cover less than 15% of the pavement area
M: D Cracks cover more than 15% of the area and are tight or cover less than 15% of the area but display pops out or can be easily removed
H: More than 15% of the area and pieces are easy to remove
Count the number of slabs at the different severity level
Linear cracking Cracks divided the slab or two or three pieces.
Can be caused by warp or friction, traffic and
repeated moisture cycling. Slabs divided into
four or more pieces are counted as divided
slabs.
L: Nonfilled less than ½ inches or any filled crack, no faulting
M: Nonfilled cracks ½ to 2 inches or any nonfilled crack up to 2 inches with less than 3/8 inches faulting or filled cracks with up to 3/8 inches faulting
H: Nonfilled cracks wider than 2 inches or filled cracks with more than 3/8 inches faulting
Count the number of slabs with each severity level
Polished aggregate Caused by repeated traffic applications. The
aggregate in the surface becomes smooth to
the touch. The measured skid resistance is low.
No severity levels are defined Count each slab with a polished condition
Pumping Ejection of material from the slab foundation
through joints or cracks. Caused by deflections of the slab by passing traffic loads.
No degrees of severity are defined One pumping joint between two joints is counted as two slabs

Table 3. Examples of Aggregate Road Surface Distress Types
(According to Hass 94)

Types of Distresses Description Severity Levels            Extent Measures

Improper cross section

Not enough crown for proper drainage. L: Small amounts of ponding water
M: Moderate amounts of ponding water
H: Large amounts of ponding water, road surface contains severe depressions
Measure linear feet along the center line of the affected area
Inadequate drainage Evaluate ability of ditches and culverts to carry away water. L: Small amounts of water ponding and/or overgrowth and debris in the ditches
M: Moderate amounts of ponding in the ditches or overgrowth and debris and erosion of the ditches into the shoulders and the roadway
Linear feet of affected area measured along the center line
Corrugations Closely spaced ridges and valleys at fairly regular intervals. L: Corrugations are less than 1 inch deep
M: Corrugations 1 to 3 inches deep
H: Corrugations more than 3 inches deep
Square feet of affected area
Potholes Bowl-shaped depressions in the road surface usually less than 3 feet in diameter. L: Less than 2 feet in diameter and less than 2 inches deep or less than 1 feet in diameter and 2 to 4 inches deep
M: More than 4 inches deep and less than 1 feet in diameter, or 2 to 4 inches deep and 1 to 2 feet in diameter, or more than 2 feet in diameter and less than
2 inches deep
H: More than 2 inches deep and more than 4 feet in diameter
Count the number of each severity level in the sample area
Ruts

Depressions in he wheel path. L: Less than 1 inch deep
M: 1 to 3 inches deep
H: More than 3 inches deep
Square feet of affected area
Loose aggregate Aggregate particles are separated. L: Loose aggregate on the road surface
M: Moderate aggregate berm on the shoulder or less traveled area; a large amount of fine area on the road
surface
H: Large aggregate berm on the shoulder and less traveled area

Linear feet parallel to the road surface

4. INVENTORY METHODOLOGY

The pavement inventory is the foundation of any roadway management system since it supports the other system components and provides the information to all components. Developing the inventory of the pavement network is one of the most important procedures in the implementation of an RMS. It must be well planned so that all data can be collected, used, and analyzed effectively in other components of the RMS. The level of detail of existing facilities in this process varies by the requirements of local government agencies. The proposed inventory should, at least, be able to answer these kinds of questions:

It is also imperative that in the proposed inventory program only necessary information be established to shorten the time and increase the cost-effectiveness of the data collection process. Data storage can be as simple as a card file, or data forms and system files can be designed and then gathered into computer applications depending on the size of the project and network. Another key element in building an RMS inventory is to determine how the network should be divided into segments, and the size and boundary of each segment. Followings are the definitions in the inventory program:

4.1. Type of Segments

The type of segments can be generally categorized into two groups:

4.2. Referencing Methods

Before the network can be divided into segments, a referencing method has to be selected. There are four basic referencing methods used to define pavement sections (Hass 1994). However, it would be the best to review the current method performed by local agencies so that the existing method versus the need of a new method can be determined. Those methods include the following:

4.3. Defining the Facility Network into Segments

The primary purpose of this task is to divide the whole network to segments so that uniform characteristic segments or similar maintenance actions used to treat those segments within the network may be grouped together. The boundary is primarily used to separate segments, not to define segments. Following are factors indicating the boundaries between segments.

Factors indicating boundary:

Manmade boundary:

Once the boundary and referencing method are chosen, the entire network can be divided into segments.

4.4. Network Level versus Project Level

The data collection process is time-consuming and expensive. Excessive data collection has created problems in implementation and in the continued use of an RMS. Before any data are collected, it is important to understand the differences between network and project level pavement management to define which level of detail is actually needed.

5. EVALUATION OF CURRENT CONDITION

Once the pavement management level has been established, it is imperative that an appropriate method be used to obtain information from selected pavements so that the data can be analyzed and used effectively regarding objectives of a project. Several methods are currently used by local government agencies to evaluate the current pavement condition. Those methods can be normally categorized into four primary groups: (1) visual inspection rating, (2) nondestructive testing (NDT), (3) destructive testing, and (4) others. The uses and applications for each method are described below:

Some local government agencies may use more than one of these techniques to obtain data from selected pavements more accurately and to better fit their needs.

5.1. Pavement Condition Rating by Visual Inspection

Visual inspection can be accomplished in two fundamental manners: (1) manual visual inspection and (2) automated visual inspection.

Establishing a data form to store data is very helpful as that ensures that all information is obtained systematically and can be easily input to generate data for computer applications, if available. The form can be either a paper or computer form depending on the data collection location, size of project and network, and budget (Hass 1994). The examples of paper forms used in the data collection in the field are provided in Appendix B.

The frequency of the inspection of pavement condition normally varies by local government agency. A two-year inspection interval is considered normal. However, our survey results described in Section 2 show that a one-year inspection interval of the current pavement condition is preferred by local government agencies. Figure 1 presents the flowchart showing broad tasks to achieve pavement condition evaluation.

5.2. Pavement Condition Index

There are many indices currently used by local government agencies to determine the pavement condition and status at the time of data collection such as Present Serviceability Index (PSI), International Roughness Index (IRI), and Riding Quality. Pavement Condition Index (PCI) is another way to define the current condition of a pavement. PCI is defined as an index reflecting the composite effects of varying distress types, severity level, and extent upon the overall condition of pavement.

PCI values range from 0 to 100, which are defined as failed and excellent condition, respectively. The PCI value is decreased by a cumulative deduct value score based upon the type, quantity, and severity level of distress and type of pavement. The mathematical expression for PCI is shown as follows:

PCI = 100 - S corrected deduct value (CDV) (1)

The qualitative expressions in term of pavement quality associated with PCI are described in Figure 2.

The types of distress are a strong indicator of pavement condition. There are several factors that combine to produce a particular type of distresses in both low-volume and built-up road pavements. These factors include pavement type, quality of material used to build the road, traffic volume, traffic load characteristics, and environmental exposure. In addition, these factors also influence the severity level, the extent, and the occurrence and frequency of the distress. Consequently, from the viewpoint of assessing pavement performance, it is essential that different values of rating be assigned to different types of distress as well as to distress severity levels and extent.

Figure 1. Condition Evaluation flowchart

Figure 1. Condition Evaluation Flow Chart

Figure 2. Qualitative Expression in Terms of Pavement Quality Associated with PCI

Figure 2. Qualitative Expression in Terms of Pavement Quality Associated with PCI

The key to a successful evaluation is to identify the different types and severity levels of pavement distresses for each type of pavement such that the actual condition of the pavement is defined and applied to calculate PCI. Appendix C presents several distress types and severity levels for low-volume flexible and built-up road pavements. After the distress types, severity, and extent on the pavement are determined, the information may be then used to compute the deduct value of the concerned pavement.

The deduct value for each type of pavement and distress is obtained separately at low, medium, and high severity levels, from the deduct value curves provided in Appendix D for the observed pavement density of distress. These deduct value curves have been derived from practical experience and engineering judgment and may change with more experience. The summation of deduct value from different severity levels for each type of distress is computed, and if there is more than one type of distress on selected pavements, the summation of all deduct values must be computed. In addition, if the summation of all deduct values is greater than 100, which is the highest score that PCI can have, the summation of all deduct values must be adjusted by using the corrected deduct value curve, given in Appendix E. After the deduct value is corrected from the curves, it is then applied in Equation 1 to determine the PCI of the evaluated segment. The flowchart presenting the procedure to calculate PCI is shown in Figure 3.

Once the PCI is determined indicating the current pavement condition, then agencies should be able to decide what strategy would be best suited to maintain or improve the pavement condition such as content and type of maintenance, rehabilitation, or reconstruction actions.

Figure 3. Flowchart Presenting the Procedure to Calculate PCI

Figure 3. Flowchart Presenting the Procedure to Calculate PCI

6. INTEGRATION OF RMS WITH GEOGRAPHICAL INFORMATION SYSTEMS

For long-term successful use of an RMS, it is significant that the data as well as the new pavement management technology be kept up-to-date. This section briefly reviews a sampling of new technologies that are beginning to impact the way agencies go about asset management such as geographic information system (GIS), the integration of a RMS with other management systems, and the approach to establishing central database.

The linking of roadway management systems to maps of the roadway network is due in part to the fact that it is often much easier to communicate some types of information about the road system using maps. In particular, these maps provide a way to display information that is easily understood by management, elected officials, and the public. Some advantages from the integration of RMS with GIS are listed below:

6.1. Systems Displaying RMS Information on Maps

There are two basic options available for agencies to display RMS information on maps:

6.2. Components of GIS

There are a number of commercially available GIS software packages; however, the basic structure of a GIS remains the same from program to program:

6.3. Approach to Establishing a Central Database

One approach to establishing the central database is using GIS as the platform. Since many utilities, such as water, sewer, telephone, and cable, often occupy the same physical right-of-way as streets, a GIS would provide an excellent basis for integrating the systems. It is important for government agencies to make sure that their existing separate infrastructure management systems can transfer information to one another when needed either by linking systems in some way or by using conversion tables between systems.

New technology with possible applications to asset management becomes available everyday. It is the maintenance manager’s responsibility to keep abreast of new testing methods, equipment, or software that could improve the asset management process. Excellent ways to monitor new technology include reading technical publications, attending conferences and workshops, and self-study.

7. GENERATING STRATEGIES AND ALTERNATIVES FOR MAINTENANCE, REHABILITATION, AND RECONSTRUCTION (MR&R) ACTIONS

Strategic RMS is the process of establishing long-range and short-range maintenance improvement goals and defining the approach to meet those goals. Maintenance can be defined as both preventive and corrective. Basically, maintenance consists of a set of activities directed toward keeping pavement in a serviceable state. The recommended alternative strategies for the pavement are based upon the pavement defect rating, pavement riding quality, pavement thickness design criteria, roadway traffic volume and truck percentage, and roadway functional classification. The basis for selecting the strategy also depends on the magnitude of the problem and the availability of resources. More factors affecting maintenance action selection include level of concern, traffic level and characteristics, soil classification, cost of action, and available budget. In addition, the overall rating, actual distresses and their causes, and performance of pavements over time should be analyzed to determine the most appropriate strategy to improve the roadway network.

A comprehensive approach to road management requires the development and use of maintenance, rehabilitation, and reconstruction strategies, in order to effectively maintain the roadway network. These MR&R strategies, when combined with specific road condition information such as pavement condition survey, pavement riding quality, and functional classification, lead to specific MR&R actions. There are five basic strategies used by most government agencies for MR&R actions:

In practice, we can decide which strategy should be applied based on evaluated PCI of the pavement within a roadway network. Without any maintenance action, the pavement performance, indicated by PCI, decreases every year. The range indicating each level of service associated with PCI is established so that the need for maintenances, type of need, and time can be then determined based upon PCI value only. The range for each level of service and types of needed maintenance actions are provided in Figure 4. Following are the definitions describing each level of service:

Figure 4. Maintenance Activity and Time for Each Level of Service Based on PCI

Figure 4. Maintenance Activity and Time for Each Level of Service Based on PCI

Once the type of maintenance is selected by local government agencies, the feasible actions for maintenance or rehabilitation can be applied subsequently based upon pavement types and types of maintenance actions. Figures 5, 6, 7, and 8 represent typical maintenance and rehabilitation feasible actions for flexible, chip seal, cold mix, and aggregate surface roads, respectively.

The selection of repair strategies can be achieved in many ways such as performing economic analysis to providing cost information and the basis for making a management decision, or decisions based on past experiences. Another method to generate repair strategies to the roadway network is the use of information collected previously. Similar to the deduct curves, this method has been based on practical experience and engineering judgment and may change with more experience. The strategy keys, level of concerns, and other values needed in the flow charts are provided in Appendix F for different pavement types. The distress types, severity level, and extent determined earlier from concerned segments are used in these flow charts to provide appropriate maintenance and repair alternatives to local government agencies.

The combination of basic strategies and repairing alternatives will guide local government agencies to efficiently improve the pavement performance of the roadway network. In other words, the broad MR&R strategy needed for the roadway network is first determined based upon only the current PCI of pavements, and then the details to repair pavement segments are generated depending on distress type, severity level, extent, and type of pavement. Therefore, local agencies are able to roughly prepare or plan their budget at both the project and network level.

Figure 5. Typical Maintenance and Rehabilitation Feasible Actions for Flexible Pavement

Figure 5. Typical Maintenance and Rehabilitation Feasible Actions for Flexible Pavement

Figure 6. Typical Maintenance and Rehabilitation Feasible Actions for Chip Seal Roads

Figure 6. Typical Maintenance and Rehabilitation Feasible Actions for Chip Seal Roads

Figure 7. Typical Maintenance and Rehabilitation Feasible Actions for Cold Mix Roads

Figure 7. Typical Maintenance and Rehabilitation Feasible Actions for Cold Mix Roads

Figure 8. Typical Maintenance and Rehabilitation Feasible Actions for Aggregate Surface Roads

Figure 8. Typical Maintenance and Rehabilitation Feasible Actions for Aggregate Surface Roads

8. PAVEMENT PERFORMANCE PREDICTION MODEL

All guidelines stated earlier provide local government agencies the information, such as the current pavement condition and the method to generate MR&R actions. Based on that information, the agencies can decide the maintenance or improvement needs for the pavements according to their budgets at the present time. However, the future tasks and MR&R actions needed for the roadway network cannot be established without a pavement performance prediction model. Pavement performance prediction is one of essential components of an RMS because it forecasts the pavement condition such that maintenance and rehabilitation strategies, schedules, and budgets can be well planned ahead of time.

The prediction model is principally developed based on PCI values previously collected from the roadway network with the view of coordinating with other components of an RMS such as the inventory methods, data collection and analysis process, and MR&R strategies established earlier. Actual PCI values may be observed from the roadway network for (1) different pavement types and (2) maintenance strategies applied on those segments. A deterioration curve may then be plotted based on the collected data between PCI value and pavement age in years starting from the most recent rehabilitation date or original construction date for a new pavement. Appendix G gives deterioration curves based upon the data collected from the field for pavements subjected to a variety of maintenance actions. We see from these deterioration curves that although different maintenance actions have similar overall deterioration behavior, the rate of deterioration varies significantly. These field measured deterioration curves may be utilized to obtain a pavement performance prediction model by developing a mathematical relation for the pavement deterioration behavior. This pavement performance prediction model may then be used to forecast the PCI value of pavement in the future based upon the previous information.

Based upon the shape of measured deterioration curves shown in Appendix G, a general expression for the curve for pavement performance prediction may be expressed as follows:

PCI = A - f (K1, K2, Age) (2)

where

A = constant number
PCI = pavement condition index of the concerned segments
K1 and K2 = constants dependent upon the maintenance strategies applied on
the roadway network
Age = pavement age in years

The parameters K1 and K2 of the prediction model may be experimentally established by plotting the constant number, A, deducted by the PCI values, (A – PCI), on the logarithmic scale, y-axis, and pavement age in years on the normal scale, x-axis. Constant number, A, is arbitrarily assumed and compared for best results. The results from the tests show that the higher A-value gives the lesser value of the squared correlation coefficient (R2). In other words, the higher number of A provides more errors to the pavement performance prediction model. The best value for constant number, A, based on the results from the test, is 105.

From the curves presented in Appendix G, the lowest and highest value of squared correlation coefficient (R2) indicating the errors of the curves are 0.9085 and 0.9963, respectively. This means that the curves represent the data very well. K1 and K2 values, provided in Table 4, vary for each type of maintenance strategy and by pavement type. The predicted curves are plotted against the measured data and presented in Appendix G. In addition, it should be noted that other factors such as traffic volume and percentage of trucks may affect the K-values, and the pavement performance prediction model may need to be modified. The effect of these factors on deterioration behavior requires more research and data information, which is beyond the scope of these guidelines.

After rearranging and substituting constant values, the pavement performance prediction model is described as follows:

PCI = 105 - f (K1, K2, Age) (3)

where

PCI = pavement condition index of concerned segments
K1 and K2 = constant value provided in Table 4 for each maintenance strategy
Age = pavement age in years

Based upon the developed pavement performance prediction model, we may conclude that the pavement deterioration occurs at exponential rates. Furthermore, we note that the parameter K1 is related to the initial pavement condition, and that a higher value of K1 corresponds to a poorer initial pavement condition. Also, the parameter K2 is related to the rate of deterioration of the pavement. A higher value of K2 yields a fasteK1r rate of deterioration for the pavement. Finally, we remark that this proposed pavement performance prediction model is based upon the data collected for 12 different types of maintenance actions, initial pavement conditions, and average daily traffic (ADT). There, it is possible that a different pavement performance prediction model may be needed for maintenance strategies not considered above.

Table 4. K1 and K2 Values Using Equation 3 to Predict PCI for Selected Pavement Age

Pavement Types

Condition

ADT

Percent Trucks

PCI = 105 - f (K1, K2, Age)

K1

K2

Slurry seal

Poor

<5,000

<5%

10.2730

0.2879

Slurry seal

Poor

>5,000

>5%

21.3210

0.2987

Slurry seal

Fair

<5,000

<5%

8.3038

0.3700

Slurry seal

Fair

>5,000

>5%

13.7270

0.3977

2" AC overlay

Poor

<5,000

<5%

13.3300

0.3169

2" AC overlay

Poor

>5,000

>5%

11.1980

0.5214

4" AC overlay

Poor

<5,000

<5%

9.0810

0.2618

4" AC overlay

Poor

>5,000

>5%

11.4360

0.2687

8" stabilized base plus 4" AC overlay

N/A

N/A

N/A

6.2921

0.2336

4" base stabilization plus double chip seal

N/A

N/A

N/A

5.0725

0.8529

8" base stabilization plus double chip seal

N/A

N/A

N/A

5.8372

0.5814

8" stabilized base plus 2" AC overlay

N/A

N/A

N/A

9.0655

0.2904

From the viewpoint of predicting pavement performance, Equation 3 may be utilized to estimate the PCI of a pavement at a selected time. Table 5 gives examples of the comparison between the actual field measured PCI and the PCI predicted using Equation 3 for two cases. An encouraging comparison is obtained between the predicted values and the measured values; however, in some cases the predicted values indicate a different qualitative pavement condition, described in Figure 2, as opposed to that indicated by the measured value.

Table 5. Examples of the Comparison between Actual PCI and Predicted PCI

Type of Pavement

Pavement Age

Actual PCI

Predicted PCI from Equation 2

Slurry seal

Poor condition

<5000 ADT

<5% trucks

0

95

94.73

1

92

91.30

2

86

86.73

3

80

80.63

4

71

72.50

5

59

61.66

6

50

47.20

7

31

27.92

Slurry seal

Poor condition

>5000 ADT

>5% trucks

0

85

83.68

1

75

76.25

2

64

66.25

3

52

52.76

4

38

34.58

Once the forecasted PCI is computed based upon the pavement performance prediction model, the agencies could efficiently plan what maintenance strategy and repair action they should apply to the roadway network in the future. Also, the schedule to perform those actions as well as the funding needs may possibly be generated for the roadway network every year at all project levels.

9. LIFE CYCLE COST ANALYSIS

A major goal of any road agency is to use public funds to provide safe, comfortable roads with the greatest possible economy. This process requires balancing priorities and making difficult decisions to manage pavements efficiently. The selection analysis of the best strategy, which provides longer service life with lower cost, involves the following considerations:

As a result of this selection analysis, a recommended action strategy may be developed for the project. This action strategy may include annual reconstruction needs, rehabilitation needs, routine and preventive maintenance needs, and anticipated strategy performance.

The economic evaluation of a maintenance strategy will include costs of providing that alternative to agencies in terms of materials, construction, maintenance, and the cost savings (salvage value) of the existing base material when it can be recycled. These are then incorporated into an economic model to determine total costs and benefits.

Economic analysis can be performed in many forms such as decision criteria and constraints, decision criteria and selection, pavement maintenance and rehabilitation cost, and life cycle cost analysis. The life cycle cost analysis is designed for low-volume to medium-volume roads including flexible, built-up, and gravel roads, and it will be discussed in this section. Some of the terms involved in the analysis are described below:

9.1. Total Cost of Each Strategy

The total cost of each strategy can be obtained from the following equations:

Total cost = MC + RehC = RecoC – Salv (4)

where

Total cost = total maintenance cost of each rehabilitation or reconstruction strategy
Salv = salvage value
MC = routine and preventive maintenance costs from year one given by

N
MC = Sum { MCj x [ 1 / (1 + i)n ] } (5)
j = 1

where

MCj = maintenance cost for each period in a cycle
(1+i)n = present worth value of one dollar
i = interest rate

and

RehC = rehabilitation cost for the selected strategy given by

RehC = Sum [ RehCj+ PreC ] (6)

where

RehCj = total cost of rehabilitation strategy
PreC = total cost of pavement preparation prior to rehabilitation application

This cost can be determined based on existing PCI, which will show the extent of exiting pavement deterioration.

and

RecoCj = total reconstruction cost for selected strategy

RecoCj = Sum [ RecoCj + Salvj] [ 1 / (1+i)n ] (7)

where

RecoCj = reconstruction cost
Salvj = cost saving due to salvage value of existing pavement reprocessing or reworking


In addition, construction staging cost must also be considered in the life cycle cost analysis. Most of the existing pavement management systems available today ignore this cost in determining the economic evaluation of MR&R actions. The total costs used by these systems are based on user costs such as travel time and vehicle operation costs, and agency costs such as initial construction, maintenance, and rehabilitation costs. These systems claim that the delay and increasing vehicle operation costs during the construction appropriately account for the construction staging cost. However, it is not appropriate to include low-volume road user costs in the economic evaluation because delay and vehicle operation are not significant enough to be considered in the economic evaluation, nor do the user costs represent agency expenditures. In fact, the user costs are subject to a high degree of uncertainty and are, therefore, not precise enough to yield definitive solutions to problems. Therefore, it is suggested that for the selection of the best type of strategy for low-volume road pavements, local government agencies should limit calculations to agency costs alone and should consider construction-staging cost.

When all the alternative design strategies have been analyzed and evaluated, an optimization is conducted to select the best strategy with the least total costs. The manager should make the final subjective selection of a maintenance strategy for implementation.

10. PRIORITY PROGRAMMING

A primary objective of the maintenance priority program is to determine the optimal group of construction project improvements. The priority program will determine which group of projects provides the maximum benefit subject to the constraints of available funding and compatibility requirements among projects. The best possible use of available dollars can be arrived at through a priority analysis.

Prioritizing is the overall process for producing a rank order of priority projects and project selection on the basis of factors that are important to each individual local government agency. There are several factors that should be taken into consideration in a priority program, as described below:

The priority rating indicates the priority of each strategy. Once the pavement condition indexes of the pavement surfaces are calculated and total needs are determined, priority-ranking lists for specific maintenance and rehabilitation activities must be established if the needs cannot be addressed immediately. Priorities should be created for each network segment within each strategy category. Once this type of decision is made, priorities are restricted to segments within each strategy category.

10.1. Mathematical Formulation of Priority Index

One way to classify the priority for each strategy is to assign the priority index for each activity such that all actions can be ranked numerically. From this ranking, all MR&R actions can be efficiently planned in the appropriate year of the local government agency’s short-term and long-term preparation based on the needs. Following is the formula used to calculate priority index:

Priority index = {[0.65 x PCI] + [0.10 x TF] + [0.05 x FC] + [0.10 x LF] + [0.05 x MH] + [0.05 xPRQ]} (8)

where

PCI = pavement condition index
TF = traffic factor provided in Table 6
FC = roadway functional classification factor provided in Table 7
LF = roadway location factor provided in Table 8
MH = maintenance history factor provided in Table 9
PRQ = pavement riding quality provided in Table 10

By considering all of the above factors, the priority index can be computed from Equation 8. It is essential to understand that a lower index number indicates higher priority. After the priority index for each strategy is established, this will lead agencies to successfully generate all activities needed for the improvements to fit their budgets.

Table 6. Traffic Factor Based on ADT

ADT Range

Traffic Factor (TF)

0–49

100

50–99

55

100–199

50

200–299

45

300–399

40

400–499

35

500–599

30

600–699

25

700–799

20

800–899

15

900–999

10

 1,000+

0

Table 7. Roadway Functional Classification Factor

Functional Classification

Roadway Functional Classification Factor (FC)

Major arterial

10

Minor arterial

40

Major collector

50

Minor collector

75

Local

100


Table 8. Roadway Location Factor

Roadway Location

Roadway Location Factor (LF)

Urban

0

Suburban

50

Rural

100

Table 9. Maintenance History Factor

Maintenance Cost

Maintenance History Factor (MH)

Very high

0

High

25

Average

50

Low

75

Very Low

100

Table 10. Pavement Riding Quality Factor

Pavement Condition

Pavement Riding Quality

Pavement Riding Quality Factor (PRQ)

Very good

5

100

Good

4

75

Fair

3

50

Poor

2

25

Failed

1

0

11. REPORT GENERATING METHODS

After obtaining the budget results from the RMS, the job of the pavement managers changes. The focus becomes how to “sell” the program to the elected board or council. Due to the technical nature of the data and the analysis, it is desirable to translate the findings from the RMS into clear terms that are understandable to decision makers and the public who are not technical experts or engineering professionals.

In presenting the RMS findings to the decision makers, it is important to be brief and to point out key facts that will enable them to make better decisions. Key areas of the budget presentation might address the following:

With a computerized RMS, the key factors outlined above can be accessed easily. Pavement asset management presentations to city councils and county commissions should be clear and accurate, and provide various funding alternatives.

The RMS products, usually in the form of reports or computer outputs, can be divided into different categories such as for management, engineers, boards and commissions, legislators, media, and other interest groups. Following are example of details that should be included in the report:

The number and types of reports should be carefully controlled and distributed; otherwise, potential users could be overwhelmed with information. Reports for management and legislators should be in the form of a summary with a minimum of technical detail. The reports listed previously indicate the types of information available from the RMS. Not so obvious at first is the number of RMS benefits for the agency and for the public in general. An agency will benefit by being able to maximize the effectiveness of each dollar available for maintenance and rehabilitation. And the public benefits through an asset management program that provides a maximum level of service for their tax dollars.

12. SUMMARY

The guidelines for a roadway management system (RMS) include a step-by-step procedure to assist local government agencies in coordinating, generating, and planning the maintenance, rehabilitation, and reconstruction strategies to pavements within the roadway network with the minimum cost or to fit their funds and available resources. By developing a customized RMS, local government agencies will be able to establish the data inventory, evaluate the current pavement condition, address problems on pavements, select the appropriate maintenance strategy, forecast the pavement condition in the future, perform the life cycle cost analysis, and achieve the priority program.

As a part of these guidelines, Section 2 describes the survey results conducted to gather information regarding the current roadway management practices of the local government agencies throughout the United States. It was also intended to explore information related to the roadway management tools and practices used and developed by agencies to manage their roadway networks. Moreover, a review of current issues concerning the development of an RMS is performed by searching the materials related to the RMS such as articles, technical documents developed by government agencies, and textbooks. The results from these surveys were refined, customized, and then applied to the proposed RMS guidelines.

Section 3 provides detailed background information, such as definitions and terms used in pavements, types of pavement, types of pavement distress, to encourage consistency of usage and understanding since these terms may vary from region to region and from one local government agency to another.

Section 4 provides an understanding of the data inventory methodology that is established for the data collection process. Also, this section defines the facility network in terms of segment methods that local government agencies can appropriately select regarding their available resources and their needs. In addition, the level of data for project and network levels can vary, so it is essential for local government agencies to be able to identify the difference of the level of data for both levels, which is also included in this section.

Section 5 presents the pavement condition evaluation method and procedure to perform the evaluation according to the data inventory established earlier. Although there are several indices used by local government agencies throughout the United States, the Pavement Condition Index (PCI) is considered a significant index for these guidelines to develop other components of a proposed RMS. The PCI value on the concerned pavements can be obtained by using the observed data collected from the data collection process, the deduct value curves provided in Appendix D, the corrected deduct value curves provided in Appendix E, and Equation 1. After the PCI of the concerned pavements is determined, it is then used to generate the repair and maintenance actions or compare the best alternatives for pavements in other components of the proposed RMS.

Section 6 shows the guidelines in order to integrate an RMS with geographical information systems (GIS). The integration of these systems will help local government agencies to keep pavement data up-to-date. This section also provides other advantages acquired from the integration, components of GIS, and the approach to use GIS as a platform.

Section 7 provides the method to generate strategies and alternatives for maintenance, rehabilitation, and reconstruction actions according to the PCI value obtained previously. By establishing this component of the RMS, local government agencies will be able to select the best maintenance action applied on pavements for both low-volume flexible and built-up road pavements. The flowcharts for generating maintenance strategies for these pavements are provided in Appendix F.

The pavement performance prediction model is another essential component of an RMS, presented in Section 8. This will assist local government agencies to forecast the pavement condition at a selected time. Therefore, the future tasks, needs of maintenance actions, analyzing facility life cycle cost analysis, and timing for these actions can be established to fit available funds. The pavement performance prediction model, shown in Equation 3, is obtained from the analysis of the observed data by developing a mathematical relation for the pavement deterioration behavior.

Section 9 explains the procedure to perform life cycle cost analysis, which is mostly used by local government agencies to compare alternative maintenance strategies. The total cost for each alternative can be computed by using Equations 4, 5, 6, and 7. Then, each alternative is compared to select the best strategy that will be most worth the available funds.

Section 10 provides the method to generate a priority program to determine the optimal group of construction project improvements. Prioritizing is the overall process for producing a numerical rank order of priority projects and project selection on the basis of factors that are important to each individual local government agency. This will help local government agencies generate the maintenance actions to fit their limited budget.

After a customized RMS is created for a local government agency, it is important that the RMS is understandable to those who are not technical experts or engineering professionals, such as the elected board or council. Section 11 shows some key elements and guidelines that should be included in the report to present the RMS findings to decision makers.

13. REFERENCES

Al-Swailmi, S. Framework for Municipal Maintenance Management Systems. Transportation Research Record, October 1994, 1442, pp. 3–10.

Asphalt Institute. Asphalt in Pavement Maintenance, Lexington, KY, 1983.

Haas, R., W.R. Hudson, and J. Zaniewski. Modern Pavement Management, 1994.

Hall, K.T., C.E. Correa, S.H. Carpenter, and R.P. Elliot. Rehabilitation Strategies for Highway Pavements. NCHRP Web Document 35 (Project C1-38). Transportation Research Board, Washington, DC, May 2001.

Huang, Y.H. Pavement Analysis and Design, 1993.

Liautaud, G., and A. Faiz. Simplified Rapid Assessment Approach to Road Network Management. Transportation Research Record, No. 1434, July 1996, pp. 73–76.

Medina, A., G.W. Flintsch, and J.P. Zaniewski. Geographic Information Systems-Based Pavement Management System. Transportation Research Record, No. 1652, 1999, pp. 151–157.

Moshe, L. Further Development in the Formulation of the Deterioration Curves of Overlaid. Infrastructure Condition Assessment: Art, Science, and Practice, August 1997, pp. 141–150.

Roohanirad, A. Infrastructure Asset Management Need Study Guide, Vol. 1 and 2. TransEducation Program, 2000.