Week-Beginning

Lectures (Chapter(s))

Homework /Notes                                                                       

 August 20

Intro. to Traffic Engineering (1, 2)

Conducting a literature review

 

Class notes on intro

Handout on lit review

August 27

Traffic Stream Parameters (Chapter 5); Data collection and data analysis (Chapter 7)

Traffic stream handout

Statistics handout

September 3

Speed studies (chapter 9)

Homework 1 due September 12

September 10

Tutorial on Synchro

Meet in room 134 of Town Engineering

Eric Fitzsimmons will be providing the tutorial

 

September 17

Analysis of signalized intersection

 

September 24

Exam first half

Finish analysis of signalized intersections

Chapter 21

 

Exam I

October 1

Intro to signal timing

Chapters 17 and 18

HW #2

21-1 and 21-4(a)

Class notes

October 8

 

Intro to signal timing

Overview of class project

 

Homework 3

Problems 17-2

18-1

18-2

Due Oct 29, please submit hard copy, show work

October 15

Handling left turns and misc info about signal timing

 

October 22                                                                          

Basics of conducting a traffic impact study

 

Actuated signal timing

Chapter 20

Notes from TIS

October 29

Finish actuated signal timing

 

 

November 5

Exam II first 1.25 hours

 

Pizza after test for guest speaker

 

Guest speaker:  Dr. Michael Pawlovitch (Iowa DOT) Intro to basics of crash analysis

Chapter 10

 

Exam II, exam will be open textbook but not open notes

 

November 12

Basics of traffic safety and Queuing

 

November 19

NO CLASS – Thanksgiving Recess

 

November 26

Signal Coordination

 

Stuff for final project

Duff & 3rd

Duff & 16th

Duff and 5th

Duff and Chestnut

Duff and Lincoln

 

 

Info on final project (updated 11/23)

 

AADT info from DOT

 

December 3

Simulation modeling

 

December 10

Finals week

Final project due Friday by noon – Dec 14th

 

 